The modern grain storage and drying facility has been equipped with advanced technology to ensure efficient handling of large volumes of grain and rapeseed.
The project includes:
The facility provides a total storage capacity of 62,860 tonnes, enabling efficient grain and rapeseed intake, storage, and handling.
The complex also features a high-capacity internal conveying system. Grain intake from the receiving pits reaches up to 500 m³/h, while the conveying equipment downstream of the dryer operates at 145 m³/h.
At the heart of the facility is the DT 5032 dual-burner grain dryer, equipped with a water-based dust suppression system. The dryer achieves a capacity of more than 1,072 tonnes of corn per day (reducing moisture content from 30% to 15%) and 2,576 tonnes of wheat per day (from 30% to 15%), ensuring reliable operation even during peak harvest periods.
One of the investor's key requirements was to minimize dust emissions and reduce the environmental impact of the installation.
To achieve this, the dryer was equipped with a water-jacket dust suppression system and dedicated software enabling operation in ECO mode. The dryer was also engineered to minimize noise emissions. These solutions made it possible to meet strict environmental requirements while maintaining outstanding drying performance.
The Hrubieszów project marked another stage in the long-term cooperation between UNIA GRAINS and BZK Group. UNIA had previously delivered facilities for the investor in Kosów Lacki and Goświnowice, making it a natural choice as the general contractor for this strategic investment.
BZK Group is one of Poland's largest privately owned agri-food processing groups. Its companies operate in grain and oilseed processing, food production, biofuel manufacturing, and logistics and storage services. The Group's infrastructure also includes a modern storage and transshipment terminal in Hrubieszów, serving the purchase, storage, and handling of grain and rapeseed.
From the outset, this was one of the most demanding projects of its kind. The investor required the construction of a large-scale industrial grain storage and drying facility that would meet exceptionally high technological and environmental standards while being delivered within an extremely ambitious schedule.
The entire project was completed in just 13 months—from obtaining the building permit in March 2025 to receiving the occupancy permit in April 2026. UNIA GRAINS was the only contractor willing and able to undertake the project while meeting all specified technical and environmental requirements.
Additional challenges arose from difficult ground conditions. The facility was constructed on an 11,858 m² site where the lack of suitable bearing soil required piling to depths of up to 25 metres. The project also involved the construction of a 6-metre-deep process pit, necessary to connect multiple process units operating at different elevations into one fully integrated technological system.
Co-financed under Poland's National Recovery and Resilience Plan (KPO), the investment has significantly increased the storage and logistics capacity of the BZK facility in Hrubieszów. The project is an example of a state-of-the-art grain storage and drying complex designed to meet both the current and future needs of the agri-food sector.
Turnkey construction of a grain drying and storage facility comprising: